Free PMP practice · Next

PMP practice questions against PMI’s July 2026 content outline

The PMP is 180 questions in 240 minutes, with two 10-minute breaks and 170 of the questions scored. PMI’s July 2026 Examination Content Outline puts People at 33%, Process at 41% and Business Environment at 26%, and states that roughly 40% of items are predictive. PMI does not publish a passing score.

Formally the Project Management Professional (PMP) certification exam. Awarding body: Project Management Institute (PMI). Neuron Trainer is an independent study app and is not affiliated with, endorsed by or sponsored by the organization that owns this exam.

PMP at a glance, with the source for every line

Every row below is quoted from a document published by PMI and carries the date we checked it. Where PMI publishes nothing, the row says so instead of quoting a number from somewhere else.

Questions
180 questions, of which 10 are unscored pre-test questions, so 170 are scored.Source: Project Management Institute, verified 7 August 2026
Time allowed
240 minutes, with two 10-minute breaks. The first break follows the case-study section and the second falls roughly midway through the independent questions.Source: Project Management Institute, verified 7 August 2026
Official domain weights (July 2026 exam)
People 33% · Process 41% · Business Environment 26%.Source: Project Management Institute, verified 7 August 2026
Predictive versus adaptive split
Approximately 40% of the items represent predictive project management approaches; the remaining 60% is divided between adaptive/agile and hybrid approaches.Source: Project Management Institute, verified 7 August 2026
Question types
Multiple-choice single or multiple response, drag-and-drop, and practicum hands-on testing that may include tools, data and case study questions.Source: Project Management Institute, verified 7 August 2026
Eligibility
One of four paths, all with experience accrued in the last 10 years: upper-secondary completion plus 60 months leading projects; a recognized associate’s-level, higher-certificate or advanced technical/vocational program plus 48 months; a bachelor’s degree (or higher) plus 36 months; or a degree awarded by a program accredited by PMI’s Global Accreditation Center plus 24 months.Source: Project Management Institute, verified 7 August 2026
Training requirement
35 hours of project management training. Holding an active CAPM certification waives it.Source: Project Management Institute, verified 7 August 2026
Retakes
You may take the exam up to three times within your one-year eligibility period. After three attempts you must wait one year from the last attempt before reapplying.Source: Project Management Institute, verified 7 August 2026
Certification cycle
Maintained by submitting 60 professional development units (PDUs) every 3 years and paying the renewal fee.Source: Project Management Institute, verified 7 August 2026
Pass rate
Not published by PMI. PMI does not publish a pass rate for the PMP. Figures quoted elsewhere are prep-vendor estimates rather than PMI data, so we do not repeat them.Checked against: Project Management Institute, verified 7 August 2026
Passing score
Not published by PMI. PMI does not publish a passing score or a percentage for the PMP. Results are reported as an overall pass or fail with proficiency ratings by domain. Any specific “you need X%” figure you find online is a guess.Checked against: Project Management Institute, verified 7 August 2026
Exam fee
Not published by PMI. PMI states that fees are subject to membership and regional pricing rather than publishing one global number, so we do not quote a figure.Checked against: Project Management Institute, verified 7 August 2026

Always verify: PMI published an updated PMP Examination Content Outline dated July 2026, and prices the exam by membership and region. Confirm the current content outline, your eligibility path and the fee with PMI before you apply.

What PMI publishes as the official PMP blueprint

These weights are PMI's, quoted from the source below. They are the only weights on this page that describe the real exam.

Published by PMI and verified on 7 August 2026.
AreaWeight PMI publishes
Process41%
People33%
Business Environment26%

Scroll the table sideways to see every column.

Source: PMI, PMP Examination Content Outline, July 2026, verified 7 August 2026.

What our PMP question bank covers

What this app's question bank covers — our own category shares across 649 questions, not PMI's published blueprint.
CategoryQuestions in our bankShare of our bank
People
Leading, motivating, mentoring, conflict resolution, team building, stakeholder engagement
27342.1%
Process
Initiating, planning, executing, monitoring/controlling, and closing - predictive, agile, hybrid
32449.9%
Business Environment
Strategic alignment, compliance, organizational change, project value
528%

Scroll the table sideways to see every column.

Try it

4 questions from our PMP bank

Four questions from the 649 inside the app, covering business environment, people and process. Each carries the full explanation.

PMP · Free practice Every answer explained. No signup, no email wall.
  1. Question 1 of 4

    Which document formally justifies the investment in a project by comparing anticipated costs, benefits, and risks against the organization's strategic objectives?
    Answer and explanation

    Correct answer: Business case

    The business case is the pre-project document used to determine whether the investment is worthwhile, comparing the problem/opportunity, alternatives, and financial return against strategic goals. The project charter authorizes the project and names the project manager but does not itself contain the cost-benefit justification. The project management plan describes how the work will be executed once approved. The benefits management plan tracks benefit realization over time but is developed from, not instead of, the business case. Business Environment domain (ECO), PMBOK 7th ed. business documents concept.

  2. Question 2 of 4

    Team members on a well-compensated project report competitive salaries, comfortable working conditions, and job security, yet engagement scores remain low. According to Herzberg's two-factor theory, which action is MOST likely to increase motivation?
    Answer and explanation

    Correct answer: Assign challenging stretch work with greater autonomy and opportunities for recognition

    Herzberg's theory distinguishes hygiene factors (pay, working conditions, job security), which prevent dissatisfaction but do not drive motivation, from motivators (achievement, recognition, growth, responsibility), which genuinely increase engagement. Since salary, conditions, and security are already satisfied, further investment there yields diminishing returns. The correct answer targets true motivators. Increasing pay, improving amenities, or extending job security only reinforces hygiene factors already met and will not raise engagement.

  3. Question 3 of 4

    On a Scrum team, which artifact contains only the items the team has committed to complete during the current iteration?
    Answer and explanation

    Correct answer: Sprint backlog

    The sprint backlog is the subset of product backlog items selected for the current sprint, along with the plan for delivering them and the sprint goal; it is owned and updated by the development team throughout the iteration. The product backlog is the full, ordered list of all future work and is never scoped to a single iteration. A release backlog is not a standard Scrum artifact. An impediment log tracks blockers raised during daily standups, not committed work items.

  4. Question 4 of 4

    Which of the following BEST describes the purpose of organizational change management in the context of a project?
    Answer and explanation

    Correct answer: To prepare, equip, and support individuals to successfully adopt a change

    Organizational change management focuses on the people side of change—preparing, equipping, and supporting stakeholders so a new process, system, or structure is successfully adopted and sustained, directly tied to project value delivery. Developing a schedule baseline is a planning process group activity unrelated to adoption. Earned value calculations (CPI/SPI) measure cost and schedule performance, not change adoption. Risk identification addresses uncertainty, not stakeholder readiness for change.

What actually trips people up on the PMP

Business Environment, at 26% and thin in our bank

PMI’s July 2026 content outline puts Business Environment at 26% of the exam. It covers compliance, organizational change, project value and reacting to shifts in the external environment. We will say the awkward part out loud: our bank holds 52 Business Environment questions out of 649, which is 8%, so it under-covers this domain against that outline. Drill it from PMI’s outline as well as from us until we rebalance the bank.

Situational judgment, not recall

People is 33% of the exam and almost every item is a scenario asking what a project manager should do FIRST or what is MOST appropriate. Two of the four options are usually defensible. The tested skill is picking the servant-leadership response over the directive one, and picking facilitation over escalation.

Agile and hybrid, at 60% of items

PMI states that roughly 40% of items represent predictive approaches and the remaining 60% is adaptive/agile and hybrid. If your day job is waterfall, that is the majority of the exam sitting outside your experience. Scrum artifacts, Kanban flow and hybrid trade-offs are examinable across all three domains, not quarantined into one.

The application before the exam

PMP is the only exam here where the paperwork can fail you before you sit. Experience must be non-overlapping, accrued in the last 10 years, and leading projects rather than working on them. PMI audits, and an audit failure costs you the cycle.

How long to study: six weeks, weighted to the July 2026 outline

Six weeks is the shape below, plus a week zero for the application. Our bank holds 649 questions split 324 Process · 273 People · 52 Business Environment. That is 8% in Business Environment against the 26% PMI’s July 2026 outline gives it, so plan your own time to the outline and use the bank where it is strongest.

Week 0: the application

Map your experience to one of PMI’s four eligibility paths and get the 35 training hours documented. Do this before you study anything, because an audit stops the clock.

Weeks 1–2: Process

324 questions, the biggest block in the bank and 41% of the exam. Work predictive and agile side by side rather than sequentially, because the exam interleaves them deliberately.

Weeks 3–4: People

273 questions, 33% of the exam, and almost all scenario-based. Answer, then read the explanation even when you were right. The reasoning is the transferable part; the scenario is not.

Week 5: Business Environment, from PMI’s outline

26% of the current exam and the thinnest part of our bank. Drill our 52 questions, then work directly from PMI’s July 2026 content outline for compliance, governance and external-environment tasks.

Week 6: timed simulations

Run full 180-question simulations. Note that the in-app simulator is set to a 230-minute limit, against the 240 minutes PMI publishes.

Is the PMP hard?

PMI does not publish a pass rate or a passing score for the PMP, so nobody can honestly tell you what percentage you need. You get an overall result plus proficiency ratings by domain, and that is deliberate: the exam is scored against a standard rather than against other candidates.

The difficulty is judgment rather than recall. Most items are scenarios asking what a project manager should do first, and two of the four options are usually defensible. Roughly 60% of items represent adaptive, agile or hybrid approaches, so if your working life is predictive, the majority of the exam sits outside your daily experience.

The July 2026 content outline is the one to study against. It puts Business Environment at 26% of the exam, so compliance, governance, organizational change and external-environment questions are a quarter of your marks. Our own bank holds 52 of 649 questions there, which is 8%, so it under-covers that domain. If your material predates the July 2026 outline, reconcile it against PMI’s current one before you rely on it.

How the PMP differs from the exams beside it

PMI publishes a July 2026 content outline for the PMP, and Business Environment carries 26% of the exam under it: governance, compliance, organizational change and external-environment items are a quarter of your marks. It is also the only exam here with a real experience gate, 24 to 60 months of leading projects depending on your education, and the only one whose sponsor tells you the format precisely while declining to tell you the pass mark at all.

Questions people actually ask about the PMP

How many questions is the PMP exam and how long is it?

180 questions in 240 minutes, with two 10-minute breaks. Ten of the 180 are unscored pre-test items, so 170 count. PMI publishes this in its July 2026 content outline.

What is the passing score for the PMP?

PMI does not publish one. You get an overall pass or fail plus proficiency ratings by domain. Any specific percentage you see quoted is somebody’s estimate, not PMI’s number.

Is the PMP hard?

PMI publishes neither a pass rate nor a passing score, so nobody can honestly put a number on it. The difficulty is judgment rather than recall: most items are scenarios asking what a project manager should do first, and two of the four options are usually defensible. Roughly 60% of items sit outside predictive approaches.

What does PMI’s July 2026 PMP content outline say?

It sets the domain weights at People 33%, Process 41% and Business Environment 26%, and lists multiple choice, drag-and-drop and practicum items using tools, data and case studies among the question types. We quote only what that outline states, so we do not publish before-and-after percentages we cannot source to PMI.

What do I need to be eligible for the PMP?

One of four paths, all with experience from the last 10 years: upper-secondary education plus 60 months leading projects, a post-secondary short-cycle qualification plus 48 months, a bachelor’s degree plus 36 months, or a degree from a PMI GAC-accredited program plus 24 months. Everyone also needs 35 hours of training unless they hold an active CAPM.

How much of the PMP is agile?

PMI states that approximately 40% of items represent predictive approaches and the other 60% is split between adaptive/agile and hybrid. Those items are spread across all three domains rather than grouped together.

How many attempts do I get at the PMP, and how long does it last once I pass?

Three attempts inside your one-year eligibility period; after the third you wait a year from that attempt before reapplying. Once you pass, PMI runs the certification in three-year cycles, kept current with 60 PDUs and the renewal fee.

Are these real PMP questions?

No, and we would not do that. Live PMP items are protected by PMI’s exam security rules. Everything in our bank is written from scratch against PMI’s published domain structure, pitched at the same difficulty, and shipped with an explanation covering the right answer and each distractor.

Practice another Next exam

Business, academic & admissions. Every one of these pages is built the same way: sourced facts, an honest admission where the sponsor publishes nothing, and free practice questions.

The app

The PMP app is still in development

The PMP app ships 649 questions with full explanations, split 324 process, 273 people and 52 business environment. That is 8% in business environment against the 26% PMI’s July 2026 content outline gives it, so the bank under-covers that domain, and the in-app simulator is still set to a 230-minute limit against the 240 minutes PMI publishes. We would rather say that than let you find out on exam day. Process and people coverage is strong. Smart Quiz targets weak domains, Topic Drill isolates one, the Exam Simulator runs a fixed-length timed paper, and an AI tutor explains anything the written explanation does not settle. Availability is the other thing to say plainly: the PMP app is in development, not on the App Store. The roadmap page carries its place in the queue, and the released build will be free to start with a subscription for unlimited AI explanations and the whole bank.

  • Smart Quiz — keeps returning to the categories you keep missing
  • Topic Drill — one category at a time, on its own
  • Exam Simulator — a fixed-length timed paper (180 questions in 230 minutes, as this app sets it). It does not get harder as you go; the length and the mix are fixed.
  • AI tutor — re-explains any question in plain English
  • Progress tracking, reported per category
  • On-screen calculator
  • Study reminders
  • Light and dark themes

The app calls you ready at 70% on its own simulator. That is an in-app practice target we chose, not PMI's passing standard.

Not on the App Store yet. This one is still in development, so there is nothing to download today. The practice questions above are the whole of what we can give you right now, and they are free and complete. See where it sits in the queue, or browse the apps that are live.

PMI updated the outline in July. Study that version.

The questions on this page are free to work through without an account. Process and people are where our bank is deepest; PMI’s July 2026 outline has to carry business environment until we rebalance.

See the apps that are live

Sources, and when we last checked them

This page was last reviewed on . The 9 facts quoted above were last checked against their sources on . Where PMI publishes nothing, the table above says so rather than guessing.

PMP, CAPM, PMI and PMBOK are marks of the Project Management Institute. Neuron Trainer is not affiliated with, endorsed by, or sponsored by PMI; the names are used descriptively to identify the exam this app prepares you for.